The following is the paving and milling schedule for the streets affected by the PSE&G work in town.
Street |
Between Street 1 |
Between Street 2 |
Milling Date |
Pave Date |
Fieldmere Ave |
Cornwall Rd |
Woodvale Rd |
10/22 |
10/25 |
Delmar Ave |
Cornwall Rd |
Woodvale Rd |
10/22 |
10/25 |
Woodvale Rd |
Fairmount Ave |
Prospect St |
10/22 |
10/25 |
Elmwood Ave |
Gaynor Pl |
Woodvale Rd |
10/22 |
10/25 |
Glenfair Rd |
Fairlawn Boarder |
Gaynor Pl |
10/22 |
10/25 |
Garvey Pl |
Fairlawn Boarder |
Gaynor Pl |
10/23 |
10/25 |
Gaynor Pl |
Cornwall Rd |
End |
10/23 & 10/24 |
10/28 |
Garret Pl |
Cornwall Rd |
Fairlawn Boarder |
10/24 |
10/29 |
Griswold Pl |
Cornwall Rd |
Pinelynn Rd |
10/24 |
10/29 |
Gibson Pl |
Cornwall Rd |
Fairlawn Boarder |
10/25 |
10/29 |
Gordon Pl |
Cornwall Rd |
Godfrey Ter |
10/25 |
10/29 |
George Rd |
Cornwall Rd |
Godfrey Ter |
10/25 |
10/29 |
Grover Ter |
Cornwall Rd |
Graham Pl |
10/25 |
10/29 |
Godfrey Ter |
Gibson PL |
Grover Ter |
10/25 |
10/30 |
Graham Pl |
Cornwall Rd |
Grover Ter |
10/28 |
10/30 |
Gramercy Pl |
Harristown Rd |
end of trench |
10/28 |
10/30 |
Wadsworth Rd |
Stonefield Rd |
Gramercy Pl |
10/28 |
10/30 |
Edgemont Rd |
Stonefield Rd |
Gramercy Pl |
10/28 |
10/30 |
Stonefield Rd |
Harristown Rd |
Salem Ct |
10/28 |
10/30 |
Salem Ct |
Stonefield Rd |
End |
10/28 |
10/30 |